CMHI-233 DECK COVERING KICK-OFF MEETING


发布时间:

2022-03-03

CMHI-233 heavy crane vessel is in the process of hot work and will soon be delivered to inner decorative company for deck covering installation deck by deck. In view of owner’s concern for the deck covering project, and also considering the first time to use the product from the new maker, the company attaches great importance to it.

CMHI-233 heavy crane vessel is in the process of hot work and will soon be delivered to inner decorative company for deck covering installation deck by deck. In view of owner’s concern for the deck covering project, and also considering the first time to use the product from the new maker, the company attaches great importance to it.

On March 1st of 2022, under the organization of Guo, general manger of the company, responsible persons in charge of construction, technology, makers and shipyard attended the meeting.

The meeting mainly discussed the time plan, working procedure arrangement, material management, construction organization and key nodes of deck covering installation. People who attended the meeting expressed their views and suggestions to later construction.

The installation of deck covering will be expected to start on March 8th from E deck.